Upcoming works on A22 - New roundabout

Update 10.09.2020:

For information………

‘night closures will be in place Monday – Thursday next week. Thereafter, night closures will be in place Monday to Friday until early December.

We will continue to update the variable message signs to keep drivers informed.'


The current earthworks operation has progressed well and is ahead of programme. This means that the introduction of the temporary 30mph speed limit and 2 way traffic control will now be bought forward by one week, as set out below:

  • Phase 1 traffic management (2 way traffic lights for 3 weeks as per page 2 of the attached TM plan) on A22 Uckfield bypass to commence from Monday 17th August
  • Variable message signs to advise drivers on the A22 Uckfield bypass will be in position from Monday 3rd August.
  • The existing lay-by will be permanently closed with effect from Monday 17th August – advance warning signs will be erected to advise users.


Dan Witcher | Principal Officer (Implementation Team)

Transport Development Control, Communities Economy & Transport

Heathfield Highways Depot,

Burwash Road, Heathfield,

East Sussex, TN21 8RA

Tel: 01273 482252 | Mob: 07743 600670 | Website: www.eastsussex.gov.uk